Electricity utility · Paraíba

Solar grid connection with Energisa Paraíba

Energisa Paraíba is the electricity utility (distributor) for Paraíba. Every grid-tied solar system in its area needs its approval — the access request, the technical opinion and the inspection — before it can export energy and earn net-metering credits.

15 daysAccess opinion
7 daysInspection
7 daysConnection

About Energisa Paraíba

GroupEnergisa
Service areaParaíba

Serves the whole state of Paraíba.

Step by step

  1. Design and documentation. The installer sizes the system and gathers the technical documents: the ART/TRT of the responsible professional, the single-line diagram, the technical description and the datasheets of the inverter (with INMETRO record) and modules.
  2. Access request. The request is filed on the utility's portal, with the access request form, the consumer unit holder's documents and a recent electricity bill.
  3. Access opinion. The utility reviews the design and issues the access opinion within the legal deadline — approving it, listing requirements to fix or, when the grid needs reinforcement, indicating works.
  4. Installation. Once the opinion is approved, the plant is installed exactly as designed: modules, inverter, protections and the grid connection point.
  5. Inspection request. When the installation is finished, the installer requests the inspection from the utility — also subject to a legal deadline.
  6. Inspection and connection. The utility inspects the installation and, if everything conforms, swaps the meter for a bidirectional one and connects the system. The plant starts earning energy credits: it is approved.

Documents required

The usual set requested by Energisa Paraíba. Items marked as conditional are only needed in some cases.

DocumentWhat it is
Access request formThe utility's standard form, filled in with the consumer unit and generation data.
ID of the consumer unit holderID and tax number (CPF) for individuals, or the company registration card (CNPJ) and articles of association for companies.
Electricity billA recent bill of the consumer unit — it confirms the holder, the unit number, the tariff class and the connection type.
ART / TRT of the responsible professionalThe technical responsibility record issued by the engineer (CREA) or technician (CFT), with the fee paid.
Single-line diagramElectrical diagram of the system (grid → meter → protection → inverter → generator), signed by the responsible professional.
Technical descriptionTechnical description of the system: power, modules, inverter, protections and connection mode.
Inverter datasheet + INMETRO recordThe inverter datasheet and its INMETRO registration or certificate proving conformity.
Module datasheetDatasheet of the photovoltaic modules (power, voltage, certification).
Acknowledgement and responsibility termThe term or adhesion contract to the net-metering system, signed by the holder.
Power of attorney ConditionalNeeded when the person signing the request is not the holder of the consumer unit.
List of participating consumer units ConditionalFor remote self-consumption, shared generation or multiple units — how the credits are split between the units.

Deadlines

For micro-generation (up to 75 kW) without grid works, ANEEL Normative Resolution 1,000/2021 sets reference deadlines of 15 days for the access opinion, 7 days for the inspection and 7 days for the connection, each counted from the respective request. Mini-generation and projects that need grid reinforcement take longer.

Other utilities in the Energisa group

Grid connection in Brazil, explained Net metering under Law 14,300, the Fio B charge and how the approval works with every utility.
Read the overview

Summary of public information for orientation only. Check the utility's current technical standard and portal before filing. See the full profile in Portuguese.

Frequently asked questions

How do I connect a solar system with Energisa Paraíba?

File the access request on the Energisa Paraíba portal with the form, the holder's documents, a recent bill, the ART/TRT, the single-line diagram and the equipment datasheets. After the access opinion, install the system, request the inspection and wait for the bidirectional meter.

How long does Energisa Paraíba take to approve a solar system?

For micro-generation without grid works the reference deadlines are 15 days for the access opinion, 7 days for the inspection and 7 days for the connection, counted from each request.

Which documents does Energisa Paraíba ask for?

Usually the access request form, the consumer unit holder's documents, an electricity bill, the ART/TRT, the single-line diagram, the technical description and the datasheets of the inverter (with INMETRO record) and modules.