The legal framework
Distributed generation (DG) in Brazil is governed by Law 14,300/2022, the legal framework for micro and mini generation, and by ANEEL Resolution 1,000/2021 (updated by Resolution 1,059/2023), which sets the connection procedures and deadlines utilities must follow. ANEEL is the federal electricity regulator; the connection itself is handled by the local distribution utility (concessionária).
- Microgeneration: installed capacity up to 75 kW, usually connected at low voltage.
- Minigeneration: above 75 kW, up to 3 MW for non-dispatchable sources such as solar under the current rules (5 MW for dispatchable sources).
Net metering: the compensation system (SCEE)
Energy exported to the grid becomes kWh credits that offset the consumption of the same account, of another account with the same holder (remote self-consumption), of a shared-generation group or of units in a condominium. Credits are valid for 60 months.
Every connection still pays the minimum availability charge: the equivalent of 30 kWh/month for single-phase, 50 kWh for two-phase and 100 kWh for three-phase services.
For systems requested after 7 January 2023, Law 14,300 phases in a charge on the distribution-network portion of the tariff (the so-called Fio B) on compensated energy: 15% in 2023, 30% in 2024, 45% in 2025, 60% in 2026, 75% in 2027 and 90% in 2028, after which the rules defined by ANEEL apply. Systems requested before that date keep the previous rules until 2045.
Step by step
Design and paperwork
A registered engineer or technician signs the technical responsibility record (ART), the single-line diagram and the technical description of the system.
Access request
The installer files the request on the utility's portal with the holder's documents, the energy bill and the module and inverter datasheets.
Utility opinion
For microgeneration without grid works, the utility has 15 days to issue its opinion, approving or listing required changes.
Inspection
After installation the installer requests the inspection, which the utility must carry out within 7 days.
Connection
With the inspection approved, the utility installs the bidirectional meter and connects the system within 7 days.
Deadlines are the reference values for microgeneration without network works. Larger projects, or those requiring grid reinforcement, follow longer timelines.
Documents usually required
- Access request form of the utility
- ID of the account holder and a recent energy bill
- ART — technical responsibility record of the designer
- Single-line diagram and technical description of the system
- Datasheets of the photovoltaic modules and of the inverter
- INMETRO certificate of the inverter, when requested
- Power of attorney (when the installer files on the holder's behalf) and, for credit sharing, the list of beneficiary accounts
Datasheets for modules and inverters are available in the Silizium datasheet library.
Main utilities
Each utility runs its own portal and adds its own requirements. Open a utility for its documents, deadlines and connection steps.
| Utility | Group | State |
|---|---|---|
| Amazonas Energia | Amazonas Energia | Amazonas |
| Neoenergia Coelba | Neoenergia | Bahia |
| Enel Distribuição Ceará | Enel | Ceará |
| EDP Espírito Santo | EDP | Espírito Santo |
| Equatorial Goiás | Equatorial | Goiás |
| Equatorial Maranhão | Equatorial | Maranhão |
| Cemig D | Cemig | Minas Gerais |
| Energisa Mato Grosso do Sul | Energisa | Mato Grosso do Sul |
| Energisa Mato Grosso | Energisa | Mato Grosso |
| Equatorial Pará | Equatorial | Pará |
| Energisa Paraíba | Energisa | Paraíba |
| Neoenergia Pernambuco | Neoenergia | Pernambuco |
| Copel Distribuição | Copel | Paraná |
| Enel Distribuição Rio | Enel | Rio de Janeiro |
| Light | Light | Rio de Janeiro |
| Neoenergia Cosern | Neoenergia | Rio Grande do Norte |
| RGE Sul | CPFL Energia | Rio Grande do Sul |
| Celesc Distribuição | Celesc | Santa Catarina |
| Enel Distribuição São Paulo | Enel | São Paulo |
| CPFL Paulista | CPFL Energia | São Paulo |
| CPFL Piratininga | CPFL Energia | São Paulo |
| EDP São Paulo | EDP | São Paulo |
| Neoenergia Elektro | Neoenergia | São Paulo and Mato Grosso do Sul |
This page summarizes public regulation for orientation only; it is not legal advice. Check the utility's current technical standard before filing.